Lead Time and Minimums

Nettalco has an Integrated Planning System that allows simulating production programs, which makes it possible to deliver accurate information for production processes and shipments to its clients.

processes

  • Simulation of Production Programs

    It allows the identification of possible "bottlenecks" in order to define corrective actions to meet delivery commitments agreed with customers and reduce delivery times.

    Garment Lead Time of Production
    Solid color 8 to 10 Weeks
    Striped and/or produced with special yarns (Melange, heathers, coated etc.) 10 to 12 Weeks
    “Quick response” or re-orders 4 to 6 Weeks
    Garment Minimum Production
    Per color 800 to 1,000 Garments
    Per style 3,000 Garments